Government projects, cost tracker

What projects cost vs what was budgeted

$134.24 billion

In cost increases across 104 federal and state government projects, sourced from Auditor-General reports across 5 states. 80 still in progress, 24 completed.

Filters and sort

104 projects

Sorted by overrun $
  • FederalIn progress
    Inland Rail
    Independent review found costs increased from $9.3B (2017) to at least $31.4B. Northern sections placed on indefinite hold.
    TransportStarted 2018
    $22,100,000,000
    +238% over budget
    Budget $9,300,000,000
    Cost $31,400,000,000
    Completion 2027
  • NSWIn progress
    Sydney Metro West
    NSW Audit Office reported costs estimated at $27-29B, up from the initial $12B estimate, due to scope and market pressures.
    TransportStarted 2020
    $16,000,000,000
    +133% over budget
    Budget $12,000,000,000
    Cost $28,000,000,000
    Completion 2030 > 2032 (+2y)
  • QLDIn progress
    Cross River Rail
    QAO reported the project's cost increased from $5.4B at 2017 approval to over $19B with services delayed to 2029.
    TransportStarted 2019
    $13,600,000,000
    +252% over budget
    Budget $5,400,000,000
    Cost $19,000,000,000
    Completion 2024 > 2029 (+5y)
  • NSWIn progress
    Sydney Metro City and Southwest
    NSW Audit Office reported costs increased from $12B business case to $22-23B due to COVID, inflation and scope.
    TransportStarted 2017
    $11,000,000,000
    +92% over budget
    Budget $12,000,000,000
    Cost $23,000,000,000
    Completion 2024 > 2026 (+2y)
  • VICIn progress
    North East Link
    VAGO reported costs increased from $15.8B to $26.2B following design and scope changes in 2018.
    TransportStarted 2019
    $10,410,000,000
    +66% over budget
    Budget $15,800,000,000
    Cost $26,210,000,000
    Completion 2027 > 2031 (+4y)
  • FederalIn progress
    Snowy 2.0
    Costs grew from $2B announced in 2017 to $12B after a 2023 contract reset. The cited 2022 ANAO audit examined early-implementation governance.
    EnergyStarted 2019
    $10,000,000,000
    +500% over budget
    Budget $2,000,000,000
    Cost $12,000,000,000
    Completion 2024-25 > 2029 (+4y 6m)
  • QLDIn progress
    CopperString 2.0
    QAO reported CopperString transmission project costs grew from $5B to $13.9B under QIC oversight review.
    EnergyStarted 2023
    $8,900,000,000
    +178% over budget
    Budget $5,000,000,000
    Cost $13,900,000,000
    Completion 2029 > 2032 (+3y)
  • VICIn progress
    West Gate Tunnel
    Cost rose from the $5.5B announced in 2015 to about $10B by completion, after contaminated-soil disputes and scope changes. The cited 2019 VAGO audit valued it at $6.7B.
    TransportStarted 2018
    $4,500,000,000
    +82% over budget
    Budget $5,500,000,000
    Cost $10,000,000,000
    Completion 2022 > 2025 (+3y)
  • NSWCompleted
    WestConnex
    NSW Audit Office found $4.3B of related costs were funded outside the $16.8B WestConnex budget.
    TransportStarted 2015
    $4,260,000,000
    +25% over budget
    Budget $16,812,000,000
    Cost $21,072,000,000
    Completion 2023
  • QLDIn progress
    Borumba Pumped Hydro Energy Storage
    QAO reported estimated costs increased from $14.2B to $18.4B due to scope, escalation and labour costs.
    EnergyStarted 2023
    $4,200,000,000
    +30% over budget
    Budget $14,200,000,000
    Cost $18,400,000,000
    Completion 2032 > 2035 (+3y)
  • FederalIn progress
    OneSKY Air Traffic Management System
    ANAO reported program costs grew from $906M approved in 2014 to over $4.1B, with delivery delayed by more than 8 years.
    ITStarted 2014
    $3,204,000,000
    +354% over budget
    Budget $906,000,000
    Cost $4,110,000,000
    Completion 2018 > 2026 (+8y)
  • QLDIn progress
    Paradise Dam Improvement Project
    QAO reported the project's cost increased from $1.2B to $4.4B after the dam wall required a complete rebuild.
    OtherStarted 2020
    $3,200,000,000
    +267% over budget
    Budget $1,200,000,000
    Cost $4,400,000,000
  • VICIn progress
    Level Crossing Removal Program
    VAGO reported program costs grew from the $5-6B election commitment to $8.3B as of July 2017.
    TransportStarted 2015
    $2,800,000,000
    +51% over budget
    Budget $5,500,000,000
    Cost $8,300,000,000
    Completion 2022 > 2025 (+3y)
  • QLDIn progress
    Queensland Train Manufacturing Program
    QAO reported the train manufacturing program budget increased from $7.1B to $9.5B post-tender.
    TransportStarted 2022
    $2,400,000,000
    +34% over budget
    Budget $7,100,000,000
    Cost $9,500,000,000
    Completion 2032
  • VICCompleted
    Melbourne Metro Tunnel
    VAGO reported total project costs increased from $10.9B approved budget to over $12.8B.
    TransportStarted 2017
    $1,900,000,000
    +17% over budget
    Budget $10,900,000,000
    Cost $12,800,000,000
    Completion 2025 (+9m)
  • QLDIn progress
    Coomera Connector Stage 1
    QAO reported the Coomera Connector cost estimate increased from $2.2B to $3.5B during construction.
    TransportStarted 2022
    $1,300,000,000
    +59% over budget
    Budget $2,200,000,000
    Cost $3,500,000,000
    Completion 2025 > 2027 (+2y)
  • NSWCompleted
    CBD and South East Light Rail
    NSW Audit Office reported total project costs exceeded $3.1B, above the $2.1B revised 2014 budget.
    TransportStarted 2015
    $1,000,000,000
    +48% over budget
    Budget $2,100,000,000
    Cost $3,100,000,000
    Completion 2018 > 2020 (+2y)
  • QLDIn progress
    Rockhampton Ring Road
    QAO reported the Rockhampton Ring Road estimate increased from $1.1B to $2B before main works began.
    TransportStarted 2025
    $900,000,000
    +82% over budget
    Budget $1,100,000,000
    Cost $2,000,000,000
    Completion 2028 > 2030 (+2y)
  • NSWIn progress
    Critical Communications Enhancement Program
    NSW Audit Office reported estimated capital cost grew from $400M in 2016 to $1.293B, with completion delayed seven years to 2027.
    ITStarted 2016
    $893,000,000
    +223% over budget
    Budget $400,000,000
    Cost $1,293,000,000
    Completion 2020 > 2027 (+7y)
  • NSWIn progress
    New Bankstown Hospital
    NSW Audit Office reported Bankstown Hospital investment increased from $1.3B to $2B.
    HealthStarted 2022
    $700,000,000
    +54% over budget
    Budget $1,300,000,000
    Cost $2,000,000,000
    Completion 2028 > 2032 (+4y)
  • FederalIn progress
    Hunter Class Frigate Design Contract
    ANAO reported the Hunter class design contract increased by $693M (36%) through 36 price-impacting changes.
    DefenceStarted 2018
    $693,000,000
    +36% over budget
    Budget $1,904,000,000
    Cost $2,597,000,000
    Completion 2024 > 2026 (+1y 6m)
  • FederalIn progress
    Collins Class Submarine Life of Type Extension
    ANAO found the LOTE design contract grew from $125M to $813M through 53 amendments, with accumulated delays.
    DefenceStarted 2022
    $688,000,000
    +550% over budget
    Budget $125,000,000
    Cost $813,000,000
    Completion 2026 > 2032 (+6y)
  • VICIn progress
    Murray Basin Rail Project (regional various)
    VAGO reported the project's TEI increased from $220M to $886M.
    TransportStarted 2014
    $665,720,000
    +303% over budget
    Budget $220,000,000
    Cost $885,720,000
    Completion 2018
  • VICIn progress
    Building a world class hospital for Frankston families (Frankston)
    VAGO reported the project's TEI increased from $562M to $1.1B.
    HealthStarted 2019
    $558,084,000
    +99% over budget
    Budget $562,000,000
    Cost $1,120,084,000
    Completion 2025 > 2026 (+9m)
  • VICIn progress
    Building a better hospital for Melbourne's inner west (Footscray)
    VAGO reported the project's TEI increased from $1.5B to $2B.
    HealthStarted 2019
    $503,605,000
    +34% over budget
    Budget $1,495,000,000
    Cost $1,998,605,000
    Completion 2025 (+3m)